FOR IMMEDIATE RELEASE April 5, 2022 Bridge demolition requires closing a portion of I-94 in Detroit this weekend Fast facts: – MDOT is replacing the Grand River Avenue bridge over I-94 in Detroit. – Demolition of the Grand River overpass requires closing I-94 between I-96 and I-75 starting Friday night. – Crews will keep the westbound I-94 ramp to I-96 closed until late May.
DETROIT, Mich. - Weather permitting, Michigan Department of Transportation (MDOT) contract crews will be removing the Grand River overpass above I-94 in Detroit this weekend. This work will require closing I-94 between I-75 and I-96 starting at 9 p.m. Friday, April 8. Both directions of I-94 are expected to reopen by 5 a.m. Monday, April 11.
Westbound I-94 traffic will be detoured via southbound I-75 and westbound I-96 back to westbound I-94. Eastbound I-94 traffic will be detoured via eastbound I-96 to northbound I-75 back to eastbound I-94. All entrance ramps to eastbound I-94 from 30th Street to M-10 (Lodge Freeway), and westbound I-94 from Mt. Elliott to Linwood streets, will be closed by 9 p.m. Friday and will reopen by 5 a.m. Monday.
Starting at 5 a.m. Monday, the following closures will remain in place until late May: – The right lane of westbound I-94 from Linwood Street to I-96, and – The westbound I-94 ramp to eastbound and westbound I-96. Ramp traffic will be detoured using southbound I-75 to I-96. Detours will be posted for local traffic using Grand River Avenue over I-94.
The new overpass will replace the original structure built in 1952. All work on this $14.6 million investment is scheduled to be completed in early 2023.
Follow the I-94 modernization project on the web at https://I94Detroit.org or follow on Facebook at www.facebook.com/I94Detroit or on Twitter at www.twitter.com/I94Detroit. |