FOR IMMEDIATE RELEASE March 2, 2022 248-361-6288 [email protected]
Reminder: Bridge demolition requires closing I-75 in Oakland County this weekend Fast facts: – I-75 will be closed between I-696 and I-75 Business Loop (Square Lake Road) starting Friday night. – 13 Mile Road will be closed under I-75 until Monday morning. – Local traffic will be able to enter northbound I-75 at 14 Mile, Rochester, Big Beaver, and Crooks roads.
MADISON HEIGHTS, Mich. - Weather permitting, the rebuilding of I-75 in Oakland County continues Friday night with a freeway closure for bridge demolition.
The freeway will be closed in both directions between I-696 and the I-75 Business Loop (Square Lake Road) to complete demolition of the overpasses at Gardenia and Lincoln avenues. In addition, 13 Mile Road will close between Stephenson Highway and Agnello Drive to allow crews to safely remove the bridge that carries northbound I-75 over 13 Mile Road. A detour will be posted.
The freeway closure will begin at 11 p.m. Friday, March 4, and will reopen to traffic by 5 a.m. Monday, March 7. Prior to the freeway closure, crews will begin closing ramps at 9 p.m. and start freeway lane closures at 10 p.m. All ramps to northbound I-75 will be closed from I-696 to 14 Mile Road. All ramps to southbound I-75 will be closed from M-59 to 11 Mile Road.
During the closure, northbound I-75 traffic will be detoured west on I-696 to northbound M-1 (Woodward Avenue), then eastbound Square Lake Road back to northbound I-75. Entrance ramps to northbound I-75 will remain open from 14 Mile Road to Crooks Road/Corporate Drive for local traffic. Southbound I-75 traffic will use westbound Square Lake Road to southbound M-1, then eastbound I-696 back to southbound I-75.
Follow I-75 modernization progress on the web at www.Modernize75.com, or follow on Facebook at www.facebook.com/Modernize75 or on Twitter at www.twitter.com/Modernize75.
### Protect workers. Protect drivers. Safe work zones for all. www.Michigan.gov/
|